Album: Bellbird Park:Week18
Up

Bellbird Park Hockey Surface Redevelopment





June 2nd, 2010
After several weeks of no activity, all bar one strip of carpet has been laid. About a third of the seams have been cut and glued as well. All the fencing has been done for a while now too. It is very close to being finished now!



June 3rd, 2010
All of the carpet is now laid, and about half of the lines have been cut and laid into the edges. There is also a large amount of sand in very large bags delivered ready to get spread onto the surface.



June 4th, 2010
All of the lines except for 2 of the under 9 D's have been laid and cut. Provided the weather is ok tomorrow, these will be finished and the sand spread out onto the field. Once this is done, it is finished!




email John Alexander with any comments or suggestions.
2nd June 2010
2nd June 2010
2nd June 2010
2nd June 2010
3rd June 2010
3rd June 2010
3rd June 2010
4th June 2010
4th June 2010