Bellbird Park Hockey Surface Redevelopment





February 15th, 2010
The ground has been levelled off again, with more drainage works going on around the perimeter of the field. I will take some photos of the pavilion works also when I take the next set, as there is construction going on there too. OK, maybe in the next few days...



February 16th, 2010
The coarse crushed rocked has been spread out over the field, while the remaining drainage has been done. It is starting to look like a field now!



February 17th, 2010
The coarse gravel has been levelled out on the field today.



February 18th, 2010
The gravel has now been rolled flat, so it is really taking shape now. The next layer to go on is some fine gravel.



February 19th, 2010
The ground looks to be just rolled more level, not much else.. The grate for the stormwater drain has been installed also.




email John Alexander with any comments or suggestions.
15th Feb 2010
15th Feb 2010
15th Feb 2010
16th Feb 2010
16th Feb 2010
16th Feb 2010
17th Feb 2010
17th Feb 2010
17th Feb 2010
18th Feb 2010
18th Feb 2010
18th feb 2010
18th Feb 2010
19th Feb 2010
19th Feb 2010


Album created by album generator from D. Madison's Marginal Hacks on Wed Mar 3 17:21:55 2010