Bellbird Park Hockey Surface Redevelopment |
|
|
March 15th, 2010 Still no asphalt :( Edges fixed up a bit more. March 16th, 2010 Still no bitumen! March 17th, 2010 The sealer for the bitumen has been laid :) The edge of the field on the outside of the curbing has also been leveled out. March 18th, 2010 About three quarters of the field has been laid with bitumen. The edges have also been neatened up as well. March 19th, 2010 All of the bitumen has been laid. It's a great big tennis court or car park now! This will need to cure for about a week before the rubber goes on. The fence posts along the edge of the driveway have also been put in. email John Alexander with any comments or suggestions. |
|||